Mele Bay Cable Landing Station facility construction underway

March 31st 2013: Port Vila based construction company, RABCO, commenced Mele Bay Cable Landing Station civil works on 31st March.

The scope of work includes: Construction of the foundations for a prefabricated Landing Station and Data Centre facility in Port Vila, perimeter fencing , security facility, cable trench and ducting, and beach man hole.

This work is scheduled for completion in mid-August 2013.

 

RABCO contractors constructing Cable Landing Station footings, Mele, Port Vila

Cable Landing Station footings, Mele, Port Vila 31/3/13